GP Announces Multi-Million Dollar Project At Clarendon OSB
Georgia-Pacific recently announced a $20 million addition to its oriented strandboard (OSB) facility in Alcolu, South Carolina. The major scope of the project will be to add a third strander to the behemoth facility, which will increase the annual output of OSB products by approximately 150MMSF. Construction on the project is slated to begin in April, and the new addition is scheduled to come on-line in the first quarter of 2023.
“The addition of a third strander has always been in the plans for Clarendon,” says Tobey Elgin, Georgia-Pacific’s Director of Operations for OSB. “The site was originally designed for additional capacity, so adding this third strander will maximize the efficiency and output for the operation.”
A strander is on the green-end of the facility, or where the logs enter the process. Once the logs are debarked, they go into the strander, which processes the wooden flakes used in the OSB process.
Purchased from Grant Forest Products in 2010, Georgia-Pacific completed the construction, and the site began operations in 2013.
Approximately 100 contractors are expected during the construction phase. Once the new strander is on-line there is an expected increase in log demand.
Latest News
Rain Finally Helps Foresters Battle Wildfires In East Tennessee
Much-needed showers Monday left state foresters cautiously optimistic in their battle against a rash of wildfires that have ignited across East Tennessee over the past two weeks. Scattered showers in Anderson and Campbell counties added firefighters' ongoing efforts...
Have A Question?
Send Us A Message