New OSB Project In Alabama Gains Permitting
Peak Renewables U.S. Inc. has received required permitting for the construction and operation of a greenfield 650MMSF oriented strandboard plant in Enterprise (Coffee County), Ala.
Last February, the Enterprise City Council approved ordinances to convert a 300 acre property into an industrial property. Shortly thereafter, ACES Consulting Group, on behalf of Peak, submitted the permitting application to Alabama Dept. of Environmental Management (ADEM). ADEM subsequently granted permits for the various development and production processes during the latter quarter of 2024.
The operation calls for SYP logs to be delivered to the site by truck, followed by three rotary drum debarkers and three stranders, two parallel single-pass rotary drum dryers (along with a Biomass Energy System using two biomass-fired combustion furnaces), two blenders for mixing liquid phenol formaldehyde resin and wax emulsion, four-layer mat forming station, multi-opening press, and finishing line.
Exhaust from both dryers would be routed to a wet ESP and to an RTO. Emissions from the press would be directed through an RCO.
Some early work is being done at the site.
Peak Renewables operates an industrial wood pellet facility and cross-laminated timber and glulam facility in Dothan, Ala.
Latest News
Florida Forest Service Sets National Prescribed Fire Record
The Florida Forest Service has announced that more than 246,000 acres of Florida state forests were treated with prescribed fire last year, the highest number ever reported by any state forestry agency in the country. The Florida Forest Service administers the top...
Dump Truck Rolls Over Logger In Garage
BACKGROUND: On a spring afternoon in the Appalachians, an independent mechanic shop owner was adjusting the air brakes on a dump truck owned by a logging contractor. The mechanic asked for help from the owner of the logging company. PERSONAL CHARACTERISTICS: The...
Have A Question?
Send Us A Message