New OSB Project In Alabama Gains Permitting
Peak Renewables U.S. Inc. has received required permitting for the construction and operation of a greenfield 650MMSF oriented strandboard plant in Enterprise (Coffee County), Ala.
Last February, the Enterprise City Council approved ordinances to convert a 300 acre property into an industrial property. Shortly thereafter, ACES Consulting Group, on behalf of Peak, submitted the permitting application to Alabama Dept. of Environmental Management (ADEM). ADEM subsequently granted permits for the various development and production processes during the latter quarter of 2024.
The operation calls for SYP logs to be delivered to the site by truck, followed by three rotary drum debarkers and three stranders, two parallel single-pass rotary drum dryers (along with a Biomass Energy System using two biomass-fired combustion furnaces), two blenders for mixing liquid phenol formaldehyde resin and wax emulsion, four-layer mat forming station, multi-opening press, and finishing line.
Exhaust from both dryers would be routed to a wet ESP and to an RTO. Emissions from the press would be directed through an RCO.
Some early work is being done at the site.
Peak Renewables operates an industrial wood pellet facility and cross-laminated timber and glulam facility in Dothan, Ala.
Latest News
Nature Conservancy Protects 12,000+ Acres In South Carolina
The Nature Conservancy has purchased a conservation easement on 12,418 acres between the Savannah and Coosawhatchie rivers in South Carolina. The easement, on The Westervelt Co.’s timberlands near the towns of Allendale and Hampton, is the fourth largest in state...
Emerald Ash Borer Could Halt Mississippi Timber Industry
A shiny green bug is posing a threat to one of Warren County’s biggest industries. The invasive emerald ash borer has already invaded forestry operations in northern states. While it hasn’t shown up here yet, the pesky beetle is likely to show up in Warren County...
Have A Question?
Send Us A Message