New OSB Project In Alabama Gains Permitting
Peak Renewables U.S. Inc. has received required permitting for the construction and operation of a greenfield 650MMSF oriented strandboard plant in Enterprise (Coffee County), Ala.
Last February, the Enterprise City Council approved ordinances to convert a 300 acre property into an industrial property. Shortly thereafter, ACES Consulting Group, on behalf of Peak, submitted the permitting application to Alabama Dept. of Environmental Management (ADEM). ADEM subsequently granted permits for the various development and production processes during the latter quarter of 2024.
The operation calls for SYP logs to be delivered to the site by truck, followed by three rotary drum debarkers and three stranders, two parallel single-pass rotary drum dryers (along with a Biomass Energy System using two biomass-fired combustion furnaces), two blenders for mixing liquid phenol formaldehyde resin and wax emulsion, four-layer mat forming station, multi-opening press, and finishing line.
Exhaust from both dryers would be routed to a wet ESP and to an RTO. Emissions from the press would be directed through an RCO.
Some early work is being done at the site.
Peak Renewables operates an industrial wood pellet facility and cross-laminated timber and glulam facility in Dothan, Ala.
Latest News
John Deere, Tigercat, Others Book InWoodsExpo Space
John Deere, Tigercat and Barko, in cooperation with their respective local dealers, Stribling Equipment, MidSouth Forestry Equipment and Crouse Truck Parts & Equipment, are the first major companies to book exhibit space with InWoodsExpo 2015. The live forestry...
Hard Work Harvesting North Carolina Fraser Firs For The Holidays
The Thanksgiving turkey's not even been purchased before a host of evergreen trees start heading down from the hills, to be trucked across the Southeast and up the East Coast. Rodney Buchanan's crew has been cutting and baling fragrant Fraser firs since mid-November,...
Have A Question?
Send Us A Message