New OSB Project In Alabama Gains Permitting
Peak Renewables U.S. Inc. has received required permitting for the construction and operation of a greenfield 650MMSF oriented strandboard plant in Enterprise (Coffee County), Ala.
Last February, the Enterprise City Council approved ordinances to convert a 300 acre property into an industrial property. Shortly thereafter, ACES Consulting Group, on behalf of Peak, submitted the permitting application to Alabama Dept. of Environmental Management (ADEM). ADEM subsequently granted permits for the various development and production processes during the latter quarter of 2024.
The operation calls for SYP logs to be delivered to the site by truck, followed by three rotary drum debarkers and three stranders, two parallel single-pass rotary drum dryers (along with a Biomass Energy System using two biomass-fired combustion furnaces), two blenders for mixing liquid phenol formaldehyde resin and wax emulsion, four-layer mat forming station, multi-opening press, and finishing line.
Exhaust from both dryers would be routed to a wet ESP and to an RTO. Emissions from the press would be directed through an RCO.
Some early work is being done at the site.
Peak Renewables operates an industrial wood pellet facility and cross-laminated timber and glulam facility in Dothan, Ala.
Latest News
Sale Of N.C. State’s Hofmann Forest Leads To Legal Battle
The sale of the Hofmann Forest has been a source of discussion, conflict and protest at N.C. State since the sale was announced last spring. Recently however, people who are unhappy about the sale found a new venue in which to make their discontent known—the courtroom...
Georgia-Pacific Touts Mississippi State University As Top Provider Of New Hires
A world leader in paper and building products manufacturing is praising Mississippi State as a top producer of the company's new employees. Georgia-Pacific recently recognized the university as its No. 1 generator of total new hires from institutions of higher...
Have A Question?
Send Us A Message