Peak Renewables U.S. Inc. has received required permitting for the construction and operation of a greenfield 650MMSF oriented strandboard plant in Enterprise (Coffee County), Ala.
Last February, the Enterprise City Council approved ordinances to convert a 300 acre property into an industrial property. Shortly thereafter, ACES Consulting Group, on behalf of Peak, submitted the permitting application to Alabama Dept. of Environmental Management (ADEM). ADEM subsequently granted permits for the various development and production processes during the latter quarter of 2024.
The operation calls for SYP logs to be delivered to the site by truck, followed by three rotary drum debarkers and three stranders, two parallel single-pass rotary drum dryers (along with a Biomass Energy System using two biomass-fired combustion furnaces), two blenders for mixing liquid phenol formaldehyde resin and wax emulsion, four-layer mat forming station, multi-opening press, and finishing line.
Exhaust from both dryers would be routed to a wet ESP and to an RTO. Emissions from the press would be directed through an RCO.
Some early work is being done at the site.
Peak Renewables operates an industrial wood pellet facility and cross-laminated timber and glulam facility in Dothan, Ala.
Latest News
Dredging Rivers For Long-Forgotten South Carolina Timber
On the Ashley River, a few miles south of Charleston, S.C., the water is murky and the marsh grass high. A three-man logging crew is cruising on a 24-foot pontoon boat. It's low tide and logs are poking out everywhere. Hewitt Emerson, owner of the Charleston-based...
N.C.’s Appalachian State Receives Grant To Develop Economical Biomass Conversion
Appalachian State University Department of Technology and Environmental Design professors David Domermuth and Ok-Youn Yu have received a $45,000 grant from the N.C. Agricultural Foundation for a project to economically convert biomass to biofuel and useful biochar....
Have A Question?
Send Us A Message