New OSB Project In Alabama Gains Permitting
Peak Renewables U.S. Inc. has received required permitting for the construction and operation of a greenfield 650MMSF oriented strandboard plant in Enterprise (Coffee County), Ala.
Last February, the Enterprise City Council approved ordinances to convert a 300 acre property into an industrial property. Shortly thereafter, ACES Consulting Group, on behalf of Peak, submitted the permitting application to Alabama Dept. of Environmental Management (ADEM). ADEM subsequently granted permits for the various development and production processes during the latter quarter of 2024.
The operation calls for SYP logs to be delivered to the site by truck, followed by three rotary drum debarkers and three stranders, two parallel single-pass rotary drum dryers (along with a Biomass Energy System using two biomass-fired combustion furnaces), two blenders for mixing liquid phenol formaldehyde resin and wax emulsion, four-layer mat forming station, multi-opening press, and finishing line.
Exhaust from both dryers would be routed to a wet ESP and to an RTO. Emissions from the press would be directed through an RCO.
Some early work is being done at the site.
Peak Renewables operates an industrial wood pellet facility and cross-laminated timber and glulam facility in Dothan, Ala.
Latest News
Louisiana Landowners Advised To Focus On Forest Productivity
Keeping sites productive in today’s economy is an important consideration to managing forestlands, according to LSU AgCenter forestry specialist Mike Blazier. With housing starts just starting to recover from an earlier slump, the market for saw timber and plywood is...
U.S. Forest Service Conducts Big Prescribed Burn In Mississippi
While it was a mostly sunny day across the Gulf Coast Monday, that was not the case in an area of northwest Jackson County. Technicians from the U.S. Forest Service performed a prescribed burn of some 2,100 acres, starting early Monday morning and working well into...
Have A Question?
Send Us A Message