New OSB Project In Alabama Gains Permitting
Peak Renewables U.S. Inc. has received required permitting for the construction and operation of a greenfield 650MMSF oriented strandboard plant in Enterprise (Coffee County), Ala.
Last February, the Enterprise City Council approved ordinances to convert a 300 acre property into an industrial property. Shortly thereafter, ACES Consulting Group, on behalf of Peak, submitted the permitting application to Alabama Dept. of Environmental Management (ADEM). ADEM subsequently granted permits for the various development and production processes during the latter quarter of 2024.
The operation calls for SYP logs to be delivered to the site by truck, followed by three rotary drum debarkers and three stranders, two parallel single-pass rotary drum dryers (along with a Biomass Energy System using two biomass-fired combustion furnaces), two blenders for mixing liquid phenol formaldehyde resin and wax emulsion, four-layer mat forming station, multi-opening press, and finishing line.
Exhaust from both dryers would be routed to a wet ESP and to an RTO. Emissions from the press would be directed through an RCO.
Some early work is being done at the site.
Peak Renewables operates an industrial wood pellet facility and cross-laminated timber and glulam facility in Dothan, Ala.
Latest News
Georgia Forest Industry Shows Growth
A new report says Georgia's forest industry added jobs in 2011 for the first time in four years. The report by Georgia Tech, conducted for the Georgia Forestry Commission, showed 46,378 workers were directly employed in forestry related jobs in 2011 — up 6.8% from the...
Controlled Forest Burning Planned For Next Eight Months On Camp Lejeune
The Camp Lejeune Environmental Management Division has started lighting prescribed burns on forestry parts of the base and plans to do so for the next eight months. The controlled burning is a tool used by forest managers both on- and off-base to help maintain open,...
Have A Question?
Send Us A Message