New OSB Project In Alabama Gains Permitting

 

 

 

Peak Renewables U.S. Inc. has received required permitting for the construction and operation of a greenfield 650MMSF oriented strandboard plant in Enterprise (Coffee County), Ala.

Last February, the Enterprise City Council approved ordinances to convert a 300 acre property into an industrial property. Shortly thereafter, ACES Consulting Group, on behalf of Peak, submitted the permitting application to Alabama Dept. of Environmental Management (ADEM). ADEM subsequently granted permits for the various development and production processes during the latter quarter of 2024.

The operation calls for SYP logs to be delivered to the site by truck, followed by three rotary drum debarkers and three stranders, two parallel single-pass rotary drum dryers (along with a Biomass Energy System using two biomass-fired combustion furnaces), two blenders for mixing liquid phenol formaldehyde resin and wax emulsion, four-layer mat forming station, multi-opening press, and finishing line.

Exhaust from both dryers would be routed to a wet ESP and to an RTO. Emissions from the press would be directed through an RCO.

Some early work is being done at the site.

Peak Renewables operates an industrial wood pellet facility and cross-laminated timber and glulam facility in Dothan, Ala.

Latest News

Virginia’s Mighty Chestnut May Yet Return To Glory

One hundred years ago the Blue Ridge Mountains were covered in American chestnut trees, which made up roughly a quarter of the canopy. The chestnut blight, an imported fungal infection first noticed in New York in 1904, had by the '50s spread throughout Appalachia and...

LP Announces Planned Restart Of Alabama Mill

What's old is now new again. The Louisiana Pacific Mill just south of Thomasville shut down three years ago due to the economy, putting hundreds out of work. Now the hiring begins as the plant gears up for reopening. "This particular project you don't have to wait for...

Have A Question?

Send Us A Message