New OSB Project In Alabama Gains Permitting
Peak Renewables U.S. Inc. has received required permitting for the construction and operation of a greenfield 650MMSF oriented strandboard plant in Enterprise (Coffee County), Ala.
Last February, the Enterprise City Council approved ordinances to convert a 300 acre property into an industrial property. Shortly thereafter, ACES Consulting Group, on behalf of Peak, submitted the permitting application to Alabama Dept. of Environmental Management (ADEM). ADEM subsequently granted permits for the various development and production processes during the latter quarter of 2024.
The operation calls for SYP logs to be delivered to the site by truck, followed by three rotary drum debarkers and three stranders, two parallel single-pass rotary drum dryers (along with a Biomass Energy System using two biomass-fired combustion furnaces), two blenders for mixing liquid phenol formaldehyde resin and wax emulsion, four-layer mat forming station, multi-opening press, and finishing line.
Exhaust from both dryers would be routed to a wet ESP and to an RTO. Emissions from the press would be directed through an RCO.
Some early work is being done at the site.
Peak Renewables operates an industrial wood pellet facility and cross-laminated timber and glulam facility in Dothan, Ala.
Latest News
NC Giving South Good Reputation In Renewable Energy
North Carolina, one of two states in the south with renewable electricity portfolio standards (REPS), is now on a path to create 12.5% of its electricity from renewable energy by 2021. Both wind and solar are limited in the state, so much of this power will need to be...
Atlanta’s ‘Treepocalypse’
The city of Atlanta, aptly nicknamed “The City in a Forest”, is looking significantly thinner these days. Giant hickories are on the ground, hundred-year-old oaks are dying and thousands of less recognized trees have ended up in the woodpile following a brutal season...
Have A Question?
Send Us A Message