New OSB Project In Alabama Gains Permitting
Peak Renewables U.S. Inc. has received required permitting for the construction and operation of a greenfield 650MMSF oriented strandboard plant in Enterprise (Coffee County), Ala.
Last February, the Enterprise City Council approved ordinances to convert a 300 acre property into an industrial property. Shortly thereafter, ACES Consulting Group, on behalf of Peak, submitted the permitting application to Alabama Dept. of Environmental Management (ADEM). ADEM subsequently granted permits for the various development and production processes during the latter quarter of 2024.
The operation calls for SYP logs to be delivered to the site by truck, followed by three rotary drum debarkers and three stranders, two parallel single-pass rotary drum dryers (along with a Biomass Energy System using two biomass-fired combustion furnaces), two blenders for mixing liquid phenol formaldehyde resin and wax emulsion, four-layer mat forming station, multi-opening press, and finishing line.
Exhaust from both dryers would be routed to a wet ESP and to an RTO. Emissions from the press would be directed through an RCO.
Some early work is being done at the site.
Peak Renewables operates an industrial wood pellet facility and cross-laminated timber and glulam facility in Dothan, Ala.
Latest News
Chip Hauler Falls Asleep at the Wheel
Background: On an early morning winter day in the Lake States Region, a driver was hauling sawmill chips to a paper mill. The driver was on his last trip after a long night shift. He was 15 miles from his delivery destination when the incident…
Western Star Hosts ALC Summer Board Meeting
Western Star Trucks recognizes “time is money” for every logger. For over 50 years, the company has built their heavy duty trucks by hand, one at a time, to ensure every truck is built to last on mountainous logging operations. Western Star also has a long history of...
Have A Question?
Send Us A Message