New OSB Project In Alabama Gains Permitting
Peak Renewables U.S. Inc. has received required permitting for the construction and operation of a greenfield 650MMSF oriented strandboard plant in Enterprise (Coffee County), Ala.
Last February, the Enterprise City Council approved ordinances to convert a 300 acre property into an industrial property. Shortly thereafter, ACES Consulting Group, on behalf of Peak, submitted the permitting application to Alabama Dept. of Environmental Management (ADEM). ADEM subsequently granted permits for the various development and production processes during the latter quarter of 2024.
The operation calls for SYP logs to be delivered to the site by truck, followed by three rotary drum debarkers and three stranders, two parallel single-pass rotary drum dryers (along with a Biomass Energy System using two biomass-fired combustion furnaces), two blenders for mixing liquid phenol formaldehyde resin and wax emulsion, four-layer mat forming station, multi-opening press, and finishing line.
Exhaust from both dryers would be routed to a wet ESP and to an RTO. Emissions from the press would be directed through an RCO.
Some early work is being done at the site.
Peak Renewables operates an industrial wood pellet facility and cross-laminated timber and glulam facility in Dothan, Ala.
Latest News
UGA Forestry School Sponsoring Logging Cost Analysis Course
The University Of Georgia’s Warnell School of Forestry & Natural Resources will sponsor a logging cost analysis course to be held June 12-13 at the Cunningham Research Station, 200 Cunningham Road, in Kinston, NC. The course will be presented by Dr. Joe Conrad, an...
Canfor Investing $40 Million To Upgrade South Carolina Sawmill
Canfor Southern Pine, a leading integrated forest products company, will invest $40 million to upgrade its existing sawmill in Camden, Kershaw County, South Carolina. A leading manufacturer of high-quality Southern yellow pine lumber, Canfor Southern Pine operates 14...
Have A Question?
Send Us A Message