New OSB Project In Alabama Gains Permitting
Peak Renewables U.S. Inc. has received required permitting for the construction and operation of a greenfield 650MMSF oriented strandboard plant in Enterprise (Coffee County), Ala.
Last February, the Enterprise City Council approved ordinances to convert a 300 acre property into an industrial property. Shortly thereafter, ACES Consulting Group, on behalf of Peak, submitted the permitting application to Alabama Dept. of Environmental Management (ADEM). ADEM subsequently granted permits for the various development and production processes during the latter quarter of 2024.
The operation calls for SYP logs to be delivered to the site by truck, followed by three rotary drum debarkers and three stranders, two parallel single-pass rotary drum dryers (along with a Biomass Energy System using two biomass-fired combustion furnaces), two blenders for mixing liquid phenol formaldehyde resin and wax emulsion, four-layer mat forming station, multi-opening press, and finishing line.
Exhaust from both dryers would be routed to a wet ESP and to an RTO. Emissions from the press would be directed through an RCO.
Some early work is being done at the site.
Peak Renewables operates an industrial wood pellet facility and cross-laminated timber and glulam facility in Dothan, Ala.
Latest News
South Carolina Forestry Commission Defends Importance Of Controlled Burns
The 2009 Highway 31 wildfire in Horry County, marked as the most destructive in the state's history, scorched 20,000 acres of land and destroyed 100 homes in the county. It was accidentally started by a man burning household garbage outside his home. While some people...
Arkansas Saw Timber Surplus May Keep Prices “Static”
Hardwood pulpwood prices should remain strong, pine pulpwood may be brighter in the coming decades, but pine saw timber will likely remain static for the foreseeable future, according to predictions for Arkansas’ $6.3 billion forest industry. Matt Pelkki, economist...
Have A Question?
Send Us A Message