New OSB Project In Alabama Gains Permitting
Peak Renewables U.S. Inc. has received required permitting for the construction and operation of a greenfield 650MMSF oriented strandboard plant in Enterprise (Coffee County), Ala.
Last February, the Enterprise City Council approved ordinances to convert a 300 acre property into an industrial property. Shortly thereafter, ACES Consulting Group, on behalf of Peak, submitted the permitting application to Alabama Dept. of Environmental Management (ADEM). ADEM subsequently granted permits for the various development and production processes during the latter quarter of 2024.
The operation calls for SYP logs to be delivered to the site by truck, followed by three rotary drum debarkers and three stranders, two parallel single-pass rotary drum dryers (along with a Biomass Energy System using two biomass-fired combustion furnaces), two blenders for mixing liquid phenol formaldehyde resin and wax emulsion, four-layer mat forming station, multi-opening press, and finishing line.
Exhaust from both dryers would be routed to a wet ESP and to an RTO. Emissions from the press would be directed through an RCO.
Some early work is being done at the site.
Peak Renewables operates an industrial wood pellet facility and cross-laminated timber and glulam facility in Dothan, Ala.
Latest News
Wood Products Leading Growth In Arkansas Economy
A federal Bureau of Economic Analysis report showing Arkansas having the nation’s fastest growing gross domestic product has led to some head-scratching among economists, but there’s little doubt that forestry is an upward mover in the state’s economy, said economist...
SGSF Committee Unveils Ambitious Agenda At 2016 Meeting
The Southern Group of State Foresters’ (SGSF) Communications Committee held its annual summer meeting in Charleston, S.C., July 25-28 to review and update its strategic plan for the coming year and begin work on several new regional outreach projects promoting...
Have A Question?
Send Us A Message