New OSB Project In Alabama Gains Permitting
Peak Renewables U.S. Inc. has received required permitting for the construction and operation of a greenfield 650MMSF oriented strandboard plant in Enterprise (Coffee County), Ala.
Last February, the Enterprise City Council approved ordinances to convert a 300 acre property into an industrial property. Shortly thereafter, ACES Consulting Group, on behalf of Peak, submitted the permitting application to Alabama Dept. of Environmental Management (ADEM). ADEM subsequently granted permits for the various development and production processes during the latter quarter of 2024.
The operation calls for SYP logs to be delivered to the site by truck, followed by three rotary drum debarkers and three stranders, two parallel single-pass rotary drum dryers (along with a Biomass Energy System using two biomass-fired combustion furnaces), two blenders for mixing liquid phenol formaldehyde resin and wax emulsion, four-layer mat forming station, multi-opening press, and finishing line.
Exhaust from both dryers would be routed to a wet ESP and to an RTO. Emissions from the press would be directed through an RCO.
Some early work is being done at the site.
Peak Renewables operates an industrial wood pellet facility and cross-laminated timber and glulam facility in Dothan, Ala.
Latest News
Rain Finally Helps Foresters Battle Wildfires In East Tennessee
Much-needed showers Monday left state foresters cautiously optimistic in their battle against a rash of wildfires that have ignited across East Tennessee over the past two weeks. Scattered showers in Anderson and Campbell counties added firefighters' ongoing efforts...
Firefighters Battling 2,000 Acre Wildfire In Tennessee County
State firefighters are continuing to battle a wildfire today in Hawkins County that has consumed about 2,000 acres on Short Mountain near Rogersville. The blaze is one of six different fire calls answered Monday in Hawkins, Scott, Grainger, Hancock, Campbell and Knox...
Have A Question?
Send Us A Message